Landscape Restoration East of Linneman to Begin

Work completed last week:
·         Met with landscape contractor to layout final restorations to be completed.

Work remaining to be completed includes:
·         Complete restoration of contractor storage area near railroad tracks east of Linneman Street.
·         Installation of trees and other vegetation along railroad tracks east of Linneman Street, to be completed in 1 to 3 weeks.  

Friday, September 11, 2015


Work completed last week:

·         No work completed.

Work remaining to be completed includes:

·         Complete restoration of contractor storage area near railroad tracks east of Linneman Street.
·         Installation of trees and other vegetation along railroad tracks east of Linneman Street, to be performed during fall months.

Monday, September 7, 2015

Landscape Restoration East of Linneman To Be Completed in Fall

Work completed last week:
·         No work completed.

Work remaining to be completed includes:
·         Complete restoration of contractor storage area near railroad tracks east of Linneman Street.
·         Installation of trees and other vegetation along railroad tracks east of Linneman Street, to be performed during fall months.