Friday, July 31, 2015

Pavement Marking Completed

Work completed last week:
·         Pavement marking along project site
·         Removal and sweeping of sand installed on driveways prior to paving final lift of asphalt
·         Saw-cutting along Linneman Street and Lehigh Avenue on east end of project.
·         Watering of sod. Sod will continue to be watered until it is established.

Work remaining to be completed includes:
·         Pavement restoration along Linneman Street east of Harlem Avenue, likely to start in 2-3 weeks.
·         Restoration of contractor storage area near railroad tracks east of Linneman Street, likely to start in 2-3 weeks.
·         Potential improvements to Harlem Avenue storm sewer