Friday, June 5, 2015

Concrete Curb & Gutter, Sidewalk, and Driveways Next Week on Dewes from Lincoln to Harlem

Work Completed Last Week:
·         Dewes Street between Spruce Street and Lincoln Street
o   No work completed
  • Dewes Street between Lincoln Street and Harlem Avenue
    • Roadway excavation
    • Installation of aggregate base course
    • Preparing for concrete curb & gutter
  • Elm Street between Dewes Street and Henley Street
    • Graded, installed topsoil, and seeded rear-yard alley.
  • Henley Street between Elm Street and Spruce Street
    • No work completed.
  • Landscaping
    • Continued to work on landscaping around detention pond.
Work Anticipated This Week:
·         Dewes Street between Spruce Street and Lincoln Street
o   No work anticipated
  • Dewes Street between Lincoln Street and Harlem Avenue
    • Preparatory work for concrete curb & gutter
    • Concrete curb & gutter installation
    • Concrete sidewalk and driveway replacement
  • Elm Street between Dewes Street and Henley Street
    • No work anticipated
  • Henley Street between Elm Street and Spruce Street
    • No work anticipated. 
  • Landscaping
    • Complete miscellaneous landscaping items.
The concrete curb & gutter, sidewalk, and driveway replacement is scheduled to start on June 8th  on Dewes Street between Harlem and Lincoln.  Please have all vehicles removed from driveways and garages by 7:00 AM on Monday, June 8thOnce the concrete work is completed, preparation work for asphalt pavement will begin. The new asphalt pavement is scheduled to be paved on June 16th, at that time residents will be allowed access to their driveways again.

Thank you for all your patience and understanding during the construction the operations.