Friday, May 8, 2015

Concrete Work on Dewes from Spruce to Lincoln Next Week

Work Completed Last Week:
·         Dewes Street between Spruce Street and Lincoln Street
o   Roadway Excavation
o   Aggregate base installation.
o   Pour concrete sidewalks
  • Dewes Street between Lincoln Street and Harlem Avenue
    • Pour concrete sidewalks
  • Elm Street between Dewes Street and Henley Street
    • Paved first 2 layers of asphalt pavement
    • Grading of landscape areas.
  • Henley Street between Elm Street and Spruce Street
    • Paved first 2 layers of asphalt pavement
    • Grading of landscape areas.
Work Anticipated This Week:
·         Dewes Street between Spruce Street and Lincoln Street
o   Complete roadway excavation
o   Complete aggregate base installation.
o   Install string line for concrete curb & gutter
o   Grade and prepare for concrete curb & gutter
o   Pour concrete curb & gutter
o   Pour concrete driveways and sidewalks

  • Dewes Street between Lincoln Street and Harlem Avenue
    • No work anticipated
    • Roadway reconstruction to begin following Memorial Day weekend.
  • Elm Street between Dewes Street and Henley Street
    • Grading of landscape areas
    • Sod installation
  • Henley Street between Elm Street and Spruce Street
    • Grading of landscape areas
    • Sod installation
  • Landscaping
    • Grade and install topsoil & seed in grassed alley between Henley Street and Dewes Street west of Elm Street
    • Install trees, sod, and natural vegetative plugs around detention pond
    • Repair damaged sod throughout Phase I Improvements
DiMeo Brothers will be starting the road reconstruction phase of the project on Monday May 12th, which includes curb and gutter installation, driveway apron repairs, and asphalt placement. Residents will be restricted from utilizing their driveways for approximately 10 days during this phase of construction. Please keep in mind that weather delays may extend the amount of time needed to complete this phase of the project.  Residents will be notified via letter if additional time is needed. We thank you for your patience and understanding during the construction process and potential weather delays. 

Thank you to all those residents that were without access to their driveways for the past 10 days along Henley Street and Elm Street. Your patience and understanding has been greatly appreciated.