Monday, May 18, 2015

Asphalt Paving Scheduled Along Dewes from Spruce to Lincoln

Work Completed Last Week:
·         Dewes Street between Spruce Street and Lincoln Street
o   Completed roadway excavation
o   Completed installation and grading of aggregate base course
o   Preparation for concrete curb & gutter, sidewalk, and driveway installation.
o   Pour concrete curb & gutter
o   Pour concrete sidewalks and driveways.
o   Asphalt driveway installation, first layer
  • Dewes Street between Lincoln Street and Harlem Avenue
    • Patching of settled trenches.
  • Elm Street between Dewes Street and Henley Street
    • Rough grading of landscape
    • Topsoil installation.
    • Asphalt driveway installation, final layer
  • Henley Street between Elm Street and Spruce Street
    • Rough grading of landscape
    • Topsoil installation
    • Asphalt driveway installation, final layer
  • Landscaping
    • Installed trees, sod, and natural vegetative plugs around detention pond
Work Anticipated This Week:
·         Dewes Street between Spruce Street and Lincoln Street
o   Fine grading of roadway in preparation of asphalt pavement
o   Paving new asphalt pavement (First 2 Layers)

  • Dewes Street between Lincoln Street and Harlem Avenue
    • Remove existing driveways and sidewalks scheduled to be replace. Temporary access will be provided until concrete work begins.
    • Roadway reconstruction to begin first week of June
  • Elm Street between Dewes Street and Henley Street
    • Sod installation
  • Henley Street between Elm Street and Spruce Street
    • Sod installation
  • Landscaping
    • Grade and install topsoil & seed in grassed alley between Henley Street and Dewes Street west of Elm Street
    • Repair damaged sod throughout Phase I Improvements
Thank you to all those residents that have been without access to their driveways due to the concrete work along Dewes Street. Your patience and understanding has been greatly appreciated. Depending on weather conditions, the asphalt paving is scheduled for early next week. Once the asphalt pavement is completed, access to driveways will be restored. 

Next week the contractor will also perform some general work site clean-up in preparation for the Memorial Day Weekend.