Material Deliveries and Prep Work On-Going

This past week, the contractor continued to mobilize equipment and making preparations for starting construction. The contractor had various material deliveries to the site along with saw-cutting the existing pavement and performing some exploratory excavations.  

 The contractor will work this Saturday, July 25th starting at 8:00 AM. Work to be performed includes constructing the temporary construction access between Henley Street and Linneman Street

Next week will start the major underground construction at Lehigh Avenue and Henley Street. The contractor will then begin installing the first large underground structure associated with the storm sewer improvements.

Depending on the work progress, the contractor will begin installing the storm sewer going west along Henley Street from Lehigh Avenue to Harlem Avenue.

The contractor will continue to install the storm sewer, sanitary sewer, and new services along Henley Street from Lehigh Avenue to Harlem Avenue for the next few weeks. 

As the construction work begins, the Village understands the impacts and inconveniences it has on the adjacent residents including dust, delays in getting around the area, and difficulty in getting to you homes. Please understand the Village will do everything possible to make the work progress a smoothly as possible to minimize these inconveniences.