Monday, October 12, 2015

Construction Completed.

Work completed last week:
·         Installation of trees and plantings on the east side of Linneman Street along the railroad tracks
·         Installation of topsoil, seed, and blanket along the east side of Linneman Street.                

Now that the final restoration along the east side of Linneman Street is done, the on-site work associated with Phase I and Phase II of the Dewes/Henley/Harlem project is completed.  

We would like to take this opportunity once again to thank all the residents that lived within the construction area and surrounding neighborhood during this 2 year project. We understand there were some significant inconveniences that you had to deal with during construction and appreciated your patience and understanding.  We are hopeful that you are satisfied with the end results of the project. 

The storm water detention pond that was constructed to help alleviate storm water flooding located behind the Glenview United Methodist Church is now fully vegetated. Stop by to take a look the next time you are in the area.  

Since the on-site construction is now completed, this will be the last blog post for the project. Thank you for following the postings and hopefully you found the information useful. 

A survey will be sent out in the coming weeks from the Village of Glenview to give you the opportunity to comment on the construction process and overall project. Please take the time to complete this survey, the information gathered is helpful as other projects are completed throughout the Village.

Monday, October 5, 2015

Landscape Restoration East of Linneman This Week.

Work completed last week:
·         No work performed on-site

Work remaining to be completed includes:
·         Complete restoration of contractor storage area near railroad tracks east of Linneman Street.
·         Installation of trees and other vegetation along railroad tracks east of Linneman Street scheduled this week.

Monday, September 28, 2015

Landscape Restoration East of Linneman to Begin

Work completed last week:
·         Met with landscape contractor to layout final restorations to be completed.

Work remaining to be completed includes:
·         Complete restoration of contractor storage area near railroad tracks east of Linneman Street.
·         Installation of trees and other vegetation along railroad tracks east of Linneman Street, to be completed in 1 to 3 weeks.  

Friday, September 11, 2015


Work completed last week:

·         No work completed.

Work remaining to be completed includes:

·         Complete restoration of contractor storage area near railroad tracks east of Linneman Street.
·         Installation of trees and other vegetation along railroad tracks east of Linneman Street, to be performed during fall months.

Monday, September 7, 2015

Landscape Restoration East of Linneman To Be Completed in Fall

Work completed last week:
·         No work completed.

Work remaining to be completed includes:
·         Complete restoration of contractor storage area near railroad tracks east of Linneman Street.
·         Installation of trees and other vegetation along railroad tracks east of Linneman Street, to be performed during fall months.

Friday, August 28, 2015

Linneman Pavement Restoration Completed. Remaining Landscape Restoration to be Completed this Fall.

Work completed last week:
·         Continued grading of contractor storage area east of Linneman Street near railroad tracks
·         Pavement removal and replacement along Linneman Street east of Harlem Avenue.
·         Installation of high-flow storm sewer grates along Lincoln Street, including curb & gutter removal and replacement.
·         Poured concrete curb & gutter on south end of Lehigh Avenue.

Work remaining to be completed includes:
·         Complete restoration of contractor storage area near railroad tracks east of Linneman Street.
·         Replacement of open grates on storm sewers along Washington Street
·         Installation of trees and other vegetation along railroad tracks east of Linneman Street, to be performed during fall months.

Monday, August 24, 2015

Restoration of Storage Area East of Linneman Street On-Going

Work completed last week:
·         Grading of contractor storage area east of Linneman Street near railroad tracks
·         Removal and replacement of sanitary sewer manhole east of Linneman Street near railroad tracks
·         Installation of storm sewer catch basin east of Linneman Street near railroad tracks.

Work remaining to be completed includes:
·         Pavement restoration along Linneman Street east of Harlem Avenue, scheduled to begin following storage area restoration.
·         Complete restoration of contractor storage area near railroad tracks east of Linneman Street.
·         Replacement of open grates on storm sewers along Washington Street
·         Installation of high-flow storm sewer grates along Lincoln Street
·         Installation of concrete curb & gutter on south end of Lehigh Avenue
·         Installation of trees and other vegetation along railroad tracks east of Linneman Street, to be performed during fall months.